To determine the procurement cost of the system, we need to add up the costs of procurement of prime mission, support equipment, and initial spares.
Procurement cost = Procurement of Prime mission + Procurement of support equipment + Procurement of Initial Spares
Substituting the given values:
Procurement cost = $800 million + $100 million + $100 million
Procurement cost = $1,000 million