8 cleaners can clean an office block in 3 hours. If two cleaners are off ill,how long will it take the rest to clean the block.

  1. 👍
  2. 👎
  3. 👁
  4. ℹ️
  5. 🚩
4 answers
  1. this is an inverse variation, so
    8/n = 6/3
    6n = 24
    n = 4

    or

    I would take 24 cleaner-hours to do the job
    so with 6 cleaners, it would take 24 cleaner hours/6 cleaners = 4 hours

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩
  2. there will be 3/4 as many cleaners, so it will take 4/3 as much time.

    what is 4/3 * 3 ?

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩
  3. thank you steve

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩
  4. thank you reiny

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩